At the end of 2007, WTVX-TV in West Palm Beach, FL, and systems integrator Burst teamed up to design and build a remotely operated and completely unattended master control facility for the station and its low-power counterparts, WTCN-LP and WWHB-LP. Six months later, this unique facility, located at the station's transmitter site in the wetlands west of Port St. Lucie, FL, was fully operational, using the same interfaces that would have been selected for an on-site operation.

When Four Points Media purchased WTVX at the end of April 2007, it became necessary for the station to build its own master control facility. Previously, CBS owned the station, and programming was switched in Miami at the CBS O&O WFOR-TV studios. Four Points Media explored several possible solutions for the new master control scenario before moving forward with the systems integrator's plan — to build the master control facility at the station's transmitter site and tie it into KUTV-TV, another Four Points outlet in Salt Lake City. This scenario proved to be both financially and technically sound; it enabled the KUTV engineering crew to remotely manage operations while allowing WTVX to maintain its local presence in West Palm Beach.

Design criteria

The project required a PC-based interface that could control an unattended and remotely controlled master control facility. The entire design was driven to accomplish this goal.

The station's new master control is operated from the KUTV master control room in Salt Lake City, despite the fact that the entire master control facility is located at the its transmitter site near Port St. Lucie. The interface for the Salt Lake City-based master control operator is an off-the-shelf computer.

In West Palm Beach, the station has a sales office, post-production capability and a small studio. Programming is received via satellite at the transmitter site and can be transmitted live or recorded to the Omneon server to be aired or file-transferred to the sales office for post production.

Because most of the systems at the master control site are computer-based, nearly everything can be seen remotely via IP. The systems that require KVM access are also viewable via KVM over IP. Media arrives at the site via satellite or by MPLS WAN, which uses Telestream's Pipeline to transfer files to the server systems at the site.

Playout can be live via satellite, delayed via MPLS WAN file transfer or live via an analog microwave link that is expected to be used only in emergencies. The WAN file transfers originate, for the most part, at the station's sales office in West Palm Beach, which is also the point of origin for the microwave link. Here, media can be posted in HD or SD formats and file-transferred to the server for playout at times assigned by automation.

Challenges

As anticipated, the parameters of the project challenged the team in many ways and called for innovation and creativity. The station's broadcast maintenance engineer, Scott Nielson, was instrumental in addressing challenges encountered during commissioning. The team had to determine how to move promotional feeds received at the transmitter site at Port St. Lucie to the sales office edit bays in downtown West Palm Beach. The solution: After recording feeds from satellite onto the server, a Telestream Flip Factory watches the server for the feeds. Once found, it transcodes the files into smaller size H.264 QuickTime movies and moves them to the editing SAN, where they are ready for editing.

Another challenge involved hosting the station's low-power stations, WTCN-LP and WWHB-LP, in West Palm Beach. These signals are carried via WTVX-DT as subchannels, and then received at their respective sites and retransmitted as LPTV signals from their original transmitter facilities. Everything runs on automation, which is also accessed remotely via KVM over IP.

The team also had to determine how to run the master control from a desktop PC located thousands of miles away. When Four Points sought the ideal solution for its master control facility, it considered nontraditional models based on computer platforms running proprietary software, but at the time, did not believe the technology was ready. Although it was necessary to be able to run the master control facility unattended, the scenario was not without risk. The transmitter site is located in a fairly remote wetland area, at the end of a road that sometimes bears more resemblance to an extended pond. On a good day, the drive to the site from West Palm Beach takes more than an hour; on a difficult day, drive time can double or triple.

Consequently, two factors were of key importance to Four Points. First, the system needed to be a highly reliable, field-tested installation using well-known solutions. And second, everything needed to be remotely rebootable. The team had to design the IP infrastructure to enable full control and monitoring, including KVM over IP connectivity.

Equipment selection

The project caused Four Points to choose technologies that could be managed remotely from a network connection. Not being able to touch the front panels of equipment creates challenges. The selection of equipment was done with these challenges in mind. Reliability was achieved by selecting equipment that has been successful in other Four Points facilities, notably KEYE-TV and KUTV-TV.

The remote reboot issue was solved by using remotely controllable power strips from Liebert. Nearly everything in the system can have its power interrupted from Salt Lake City or West Palm Beach by accessing the power manager from a desktop computer. In addition, the entire system, including the transmitter, is on a master UPS and generator.


Commenting terms of use blog comments powered by Disqus

Want to use this article?
Click here for options!
Get Copyright Clearance

Related Newsletter

News Technology Update
A twice-monthly newsletter covering the equipment used to produce the news.

Confused about the termnology in an article? Find definitions of common terms and abbreviations in Broadcast Engineering's Glossary.

 

Browse Back Issues

Resources

Broadcast Engineering Newsletters Broadcast Engineering Essential Guides Broadcast Engineering White Papers Broadcast Engineering Videos Broadcast Engineering Podcasts Broadcast Engineering Buyers Guide Broadcast Engineering Industry Calendar

Industry Calendar

Broadcast Engineering Glossary of Terms

Glossary

Broadcast Engineering RSS feed

RSS

Interactive Media

Broadcast Engineering Webinars Broadcast Engineering Training Broadcast Engineering Blogs Broadcast Engineering Forums Broadcast Engineering JobZone

JobZone

Broadcast Engineering BE Roll

Blog

 

Back to Top